Callide C Power Station
Turbine House, Boiler Structures & Coal Handling Conveyors Turbine Houses 3 & 4 and Coal Handling System
Client: Barclay Mowlem (Resource Management)
This project involved the supply and installation of 30,000 square meters of roof and wall sheeting, box gutters, down pipes and ventilation equipment.
The project has been a continuation of a mutually rewarding association with Barclay Mowlem (Resource Management) spanning almost 20 years.
Boilers 3 & 4
Client: IHI Engineering Australia
NDM Contracting’s involvement at Callide “C” led to our introduction to IHI (the Boiler supply contractor).
NDM Contracting was able to provide design assistance to modify the boiler roof structure, cladding and ventilation system. This led to the supply, by Qclad, of modified steel items and was followed by a contract to a supply package for all cladding and ventilation materials including detailed construction drawings.